Scroll through the table below to see the timeframes we're working to.
| What We're Doing | What It Means | When It's Happening |
|---|---|---|
Learning About Nature & Talking to You |
We’re surveying the land, animals, and plants and asking people what they think. |
Starting Spring 2025 |
Digging & Discovering History |
We’ll dig small trenches to learn about the ground and find any artefacts or findings |
Spring 2025 to Autumn 2025 |
Spring 2025 to Autumn 2025 |
We’ll send in plans and ask for approval to build. |
Autumn 2025 to Spring 2026 |
Getting Ready to Build |
We’ll set up the site, protect nature, and prepare the land. |
Spring 2026 to Autumn 2026 |
Building the Pipe |
This is where we’ll be laying down the pipe, building pumping stations and storage tanks and connecting everything together. |
Autumn 2026 to 2030 |
Testing the Pipe |
We’ll clean and test the pipe to make sure it works safely. |
2029- 2030 |
Restoring the land |
After building and testing the strategic pipe we’ll restore the land. |
After 2030 |
Learning About Nature & Talking to You
We’re surveying the land, animals, and plants and asking people what they think.
Starting Spring 2025
Digging & Discovering History
We’ll dig small trenches to learn about the ground and find any artefacts or findings
Spring 2025 to Autumn 2025
Spring 2025 to Autumn 2025
We’ll send in plans and ask for approval to build.
Autumn 2025 to Spring 2026
Getting Ready to Build
We’ll set up the site, protect nature, and prepare the land.
Spring 2026 to Autumn 2026
Building the Pipe
This is where we’ll be laying down the pipe, building pumping stations and storage tanks and connecting everything together.
Autumn 2026 to 2030
Testing the Pipe
We’ll clean and test the pipe to make sure it works safely.
2029- 2030
Restoring the land
After building and testing the strategic pipe we’ll restore the land.
After 2030
For any questions or further information, simply email the team: strategicpipelines@anglianwater.co.uk.